Current City Projects

Improvements are being made all around the City. If you have questions, comments or concerns about any project in the City, please do not hesitate to contact us at 616-772-0870 or by email. We are here to serve.

Elm Street Reconstruction Project

How to Access Downtown Parking During Construction

Project Schedule:

Project Bid & Award March 2017
Begin Construction April 10, 2017
Completion
August 2017 (before start of school year)

Next Week (4/17)
  • Install water main from Main to Washington
  • Install storm sewers at Main
  • Work on underdrains and conduits from Cherry to Main
Scheduled Work for Weeks of 4/24 and 5/1
  • Complete the water main between Main and Washington
  • Perform water service tie ins
  • Finish conduit work downtown
  • Complete storm sewer and underdrain work in Woonerf area
  • Begin street grading for concrete placement. Start concrete placement.
Sidewalks will remain in place for several more days from Cherry to Washington and remain in Lincoln for several weeks. This schedule is tentative and subject to change day to day.

Elm Street and Park Construction Bid Award and Budget Approval

Elm Street Woonerf Design Concept

Elm Street Change to One-Way Endorsement

Elm Street Overall Design Concept

Elm Street Development Concept

Force Main Construction & Re-Paving of Roosevelt, Oak & Ottawa Streets 



Portions of Roosevelt, Oak & Ottawa Streets will be impacted with construction and re-paving as a result of a force main construction project that will connect Holland Township with the City of Zeeland's expanded Clean Water Plant. The expansion of the plant and the connection with Holland Township is projected to be completed in August 2017. Below are the tentative construction & re-paving dates:

Tentative Project Schedule
Ottawa Street: Roosevelt to Oak and Oak Street: Ottawa to State - May 8, 2017 to May 19, 2017
Roosevelt Avenue: 100th to Ottawa and State Street Connection - June 12, 2017 to July 14, 2017

Tentative Paving Schedule
Oak Street & Ottawa Street - May 30-June 2, 2017
State Street - July 21, 2017
Roosevelt - August 1-4, 2017


Riley Street Mill & Resurface Project


Riley (State to Fairview) / Mill & Resurface
Spring / Summer - This project is slated to begin in mid June with completion projected by the end of July 2017.


101st Street Reconstruction Project


101st (BL196 to Lee) / Reconstruction / Spring/Summer

Project Schedule:

Initial Public Meeting April 12, 2017
Bid Open & Bid Award May 9, 2017 & May 15, 2017
2nd Public Meeting Late May
Begin Construction June 12, 2017
Project Completion Mid August, 2017


Transportation Study Implementation Matrix

The City of Zeeland recently engaged the services of a professional transportation engineer to evaluate a number of transportation issues within the City of Zeeland. For information on the recommended changes and implementation time frame please click here.


  1. City Services & Infrastructure


    Physical Address
    21 S Elm Street
    Zeeland, MI 49464

    Phone: 616-772-0870
    Emergency: 616-772-2001


  2. View All